Home › Guides › How to create a preventive maintenance plan: from equipment list to annual calendar
Maintenance

How to create a preventive maintenance plan: from equipment list to annual calendar

Hüseyin Şamlı · 2026-11-08 · 8 min read

A preventive maintenance plan is the annual schedule that shows which maintenance task is done on which equipment, how often and by whom. A well-built plan catches failures before they turn into downtime, shows spare-part and labour needs in advance, and answers the auditor's question "how does your maintenance system work?" in a single file. In this guide I explain how to turn an equipment list into an annual maintenance calendar, the most common mistakes and what is asked in an IATF 16949 audit; a free Excel template is at the end.

What a preventive maintenance plan is – and what it is not

The plan is the schedule of preventive maintenance: it lists the work done at fixed intervals before anything breaks. Breakdown maintenance (repairing after a failure) is not part of the plan, but breakdown records feed it: if the same failure keeps recurring on the same machine, that point needs a periodic check. Nor is the plan a work instruction. The instruction answers "how is the filter changed?"; the plan answers "which filter, when and by whom?".

Step 1: Build the equipment list

Everything starts with a complete equipment list. Give each asset a unique code and record its name, line or area, maker, model and serial number, and year of installation. Include not only production machines but also the utilities that feed them: compressors, air receivers, chillers, dryers, cranes, forklifts and switchboards. When the compressor stops, the whole plant stops; if it is not on the list, it is not in the plan.

Step 2: Carry out a criticality analysis

Applying the same maintenance intensity to every asset is expensive and unnecessary. A criticality analysis directs limited maintenance resources to the equipment with the greatest impact. A common, simple method is an A/B/C classification:

ClassCriteriaMaintenance approach
A – CriticalA stoppage affects shipments or the customer, there is no backup, there is a safety or environmental risk, product quality is directly affected.Detailed preventive plan, autonomous maintenance, predictive maintenance where useful, critical spare parts in stock.
B – ImportantA stoppage slows the line, an alternative machine or backup exists, the loss can be recovered quickly.Basic preventive plan and autonomous maintenance.
C – SupportA stoppage has little impact on production, repair is easy and cheap.Basic cleaning and inspection; run-to-failure is acceptable.

Do not let one person decide criticality. Score it in a short session with maintenance, production, quality and health and safety, and put the criteria in writing. Also consider repair time and spare-part lead time: a part with a lead time of several weeks makes the machine critical on its own.

Step 3: Define the tasks and intervals

List each task for each asset as a separate line: "Hydraulic oil filter change", "Guide lubrication check" and so on. A single line saying "general service" is useless both in the audit and on the shop floor. When setting the interval, look at four sources: the maker's operating and maintenance manual, your own breakdown history, statutory requirements and customer-specific requirements. The interval in the manual is a starting point; if breakdown records show frequent problems at one point, shorten it, and if a task has been trouble-free for years, consider extending it.

Time-based or usage-based?

Intervals can be defined in two ways. Time-based maintenance is triggered by the calendar: weekly, monthly, yearly. Usage-based (meter-based) maintenance depends on how much the equipment actually runs: operating hours, shots, cycles or kilometres. Wear-related tasks such as compressor oil, forklift service or mould maintenance are planned more accurately by meter, because a machine running one shift does not wear like one running three shifts on the same calendar.

To put usage-based tasks on the annual calendar, use average utilisation: on a compressor running 20 hours a day, a 2,000-hour service falls roughly every 100 days. If you do not read the meter regularly and update the average, the calendar drifts, so always write the meter reading in the maintenance record.

Step 4: Split the work between operators and technicians

The core idea of total productive maintenance (TPM) is that the person who knows the machine best is the operator who uses it every day. In autonomous maintenance, the operator takes over simple, frequent and standard tasks, and the maintenance team concentrates on work that needs expertise.

Operator (autonomous maintenance)Maintenance technicianExternal service / authorised person
Cleaning, checks for leaks and loose parts, oil level, pressure and temperature readings, basic lubrication, reporting abnormalitiesFilter and part changes, adjustment, measurement, electrical and hydraulic checks, overhaulWork requiring the maker's service, oil analysis, statutory periodic inspections

Prepare a short checklist with pictures for the operator's tasks and keep it at the machine. Daily checks can stay on the machine card; it is enough to put weekly and less frequent tasks in the plan. What matters is that an abnormality found by the operator turns into a maintenance request.

Step 5: Flag statutory periodic inspections separately

In Turkey, periodic inspections of lifting and conveying equipment (such as cranes and forklifts), pressure vessels, electrical installations and earthing fall under the Regulation on Health and Safety Conditions in the Use of Work Equipment. An annex to the regulation sets maximum inspection intervals by equipment type and the standards to be applied; inspections are carried out by authorised persons as defined in the regulation, and the reports are kept. Other countries have equivalent rules – for example the Betriebssicherheitsverordnung in Germany, or LOLER and PSSR in the UK.

Mark these inspections as a separate maintenance type in the plan. They do not replace your own internal maintenance: your technician checks the crane rope every month, and the annual statutory inspection is done in addition. Do not write the interval from memory; check the applicable regulation and standard for each item of equipment. Measuring equipment that needs calibration is better tracked on a separate list (IATF 16949 clause 7.1.5).

Step 6: Spread the plan over the annual calendar

Once tasks and intervals are ready, spread the plan over a 52-week calendar. Each row is a maintenance task and each column a week. When building the calendar, pay attention to the following:

How to monitor the plan

If the calendar is not compared with the work actually done, it stays on paper. Record every task with date, person, duration and findings. Key indicators:

What is asked in an IATF 16949 audit?

IATF 16949 clause 8.5.1.5 (total productive maintenance) requires a documented maintenance system: identification of key manufacturing equipment, preventive maintenance, predictive maintenance where applicable, availability of critical spare parts, and maintenance objectives that are monitored and reviewed regularly. The clause names OEE, MTBF, MTTR and preventive maintenance compliance as examples of objectives. Typical auditor questions:

  1. How did you identify your key equipment? Are your criticality criteria documented?
  2. Where is the maintenance plan for this machine, when was it last serviced and where is the record?
  3. Are there overdue tasks? What do you do when a task is late?
  4. What are your maintenance objectives and how have they developed over the last three months?
  5. Are critical spare parts in stock, and is there a list?
  6. Are the statutory inspection reports up to date?

The 5 most common mistakes

Free Excel template

The Annual Maintenance Plan template consists of an equipment list (A/B/C criticality), a maintenance plan, a 52-week calendar and a maintenance log. Intervals are entered in days, weeks, months, years or operating hours; the next due date, status (scheduled, due soon, overdue) and the calendar symbols are calculated automatically from the records. The dashboard shows plan compliance, tasks planned and done this month, overdue and upcoming tasks, a monthly plan-versus-actual chart and maintenance workload by criticality. The sample data is fictitious; enter your own equipment and start using it.

When Excel is no longer enough

Once you have hundreds of assets, meters read daily and maintenance tracked by work order, Excel becomes hard to maintain. In the Planned Maintenance section of the TAKMOS Maintenance Module, time- and meter-based plans turn into work orders when they fall due; statutory inspections and operators' autonomous maintenance checks are tracked in the same calendar.

Annual Maintenance Plan

Equipment list, A/B/C criticality, preventive maintenance plan and 53-week calendar. Next due date, overdue and upcoming tasks and plan compliance are calculated automatically from the maintenance log; the dashboard can be filtered by line.