Mould maintenance and tool life tracking: from shot counter to service plan

Hüseyin Şamlı · 2026-11-17 · 9 min read

Injection moulds and press tools are among the most expensive assets in a plant and the ones with the longest lead time. Yet in many companies mould maintenance stops at "send it to the tool room when it causes trouble", and nobody knows exactly how many shots a mould has made. In this guide I explain mould maintenance and tool life tracking step by step: the mould card, the shot counter, maintenance levels, remaining life, customer-owned tooling and what auditors ask. A free Excel template is at the end.

Why mould maintenance follows shot count, not the calendar

What wears a mould is not the calendar but the number of shots (cycles): the parting line is loaded at every closing, every ejector pin moves once per shot, every slide travels once per cycle. The same mould can run 80,000 shots one month and 5,000 the next. A "service every month" rule is late in the first month and unnecessary in the second.

That is why a mould maintenance plan is tied to the shot counter. I explained the calendar and operating-hours logic for general equipment in the guide on the preventive maintenance plan; the same logic applies to moulds, only the unit is shots.

The mould card: what to record

Every mould needs a card carrying the same number as the mould itself. Minimum content:

Expected life is the number of shots guaranteed by the toolmaker or stated in the contract. As a reference, the SPI classification widely used in the USA is roughly: Class 101 one million cycles or more, Class 102 up to one million, Class 103 up to 500,000, Class 104 up to 100,000. The tool steel, its hardness and the material moulded (glass-filled plastics are abrasive) change this figure directly.

The shot counter: three rules for counting right

  1. A shot is not a part. On an 8-cavity mould, 8,000 parts are 1,000 shots. Entering part quantities ages the mould eightfold on paper.
  2. Use a single source. The machine cycle counter, the mechanical counter on the mould or the production record: pick one and stick to it. A mechanical mould counter travels with the mould when it changes machine; it is the most reliable source.
  3. Trial and set-up shots count too. The mould wears during them as well. The gap between good parts and the counter is scrap and set-up shots; that gap is a metric in its own right.

Preventive maintenance levels

Defining three levels instead of a single "mould service" makes the work plannable for the tool room and predictable for production. The intervals below are examples; real values come from the toolmaker's recommendation and your own damage history.

LevelExample intervalWhereTypical content
Interim cleaning20–50k shots or at every mould removalOn the machine / at mould changeCleaning of parting line, vents and cavities, visual check, rust inhibitor
Minor service60–150k shotsTool room, mould openedCleaning and lubrication of ejectors, slides and guides, O-rings and seals, cooling flow check
Major overhaul200–500k shotsTool room or toolmakerFull strip-down, replacement of worn parts, dimensional check, descaling of cooling channels, surface refurbishment

A higher level includes the lower ones: after a major overhaul the interim cleaning counter is reset too. Damage repair is kept separate; it does not reset the counter and does not replace planned service. On press tools, sharpening punches and cutters usually takes the place of the minor service.

Three values are tracked per mould: shots since last service, shots left to the next service, and estimated days, found by dividing the shots left by average daily shots. When the shots left fall into the last 10–15% of the interval, the mould moves to the "due soon" list; below zero it moves to "overdue".

Tool life and remaining life

Life left = 1 − total shots / expected life. The calculation is simple; its value lies in triggering the decision in time. Example: a mould with an expected life of 600,000 shots is at 546,000 shots, so 9% of its life is left. At an average of 12,000 shots a month it reaches the end of its life in about 4.5 months. If a new mould takes 4–5 months to source, the order has to be placed today.

So set the life warning threshold by lead time rather than by percentage: the warning should come when the remaining life falls to the shots produced during the replacement mould's lead time plus sample approval. Reaching expected life does not mean the mould is scrapped either. Based on dimensions, surface condition and recent damage records you decide between extending life by overhaul, replacing worn inserts or ordering a new mould. For a customer-owned mould this decision is made with the customer.

Damage and failure records

Mould damage belongs in a separate log: date, mould, counter, damage type (flash, broken ejector, slide damage, cooling leak, hot runner failure, surface damage…), root cause, downtime and action taken. After a few months the Pareto of damage types shows where the maintenance content falls short. If hot runner failures dominate, for example, heater and thermocouple checks are added to the minor service and spares are put in stock.

If you record mould-related machine stoppages with a separate code in the breakdown log, you also see the mould's impact on production. I explained how in the guide on how to calculate MTBF and MTTR.

Customer-owned tooling

In automotive supply, many moulds belong to the customer: the customer pays for the mould and it sits in your plant. ISO 9001 clause 8.5.3 requires customer property to be identified and safeguarded and, if it is lost, damaged or found unsuitable for use, the customer to be informed and a record kept. IATF 16949 clause 8.5.1.6 (management of production tooling) additionally requires customer-owned tools to be permanently marked in a visible location so that ownership and application can be determined.

In practice this means an ownership column in the mould list, a permanent label or engraving on the mould, and a "customer notified" column in the damage log. Most customer-specific requirements also ask for customer approval before scrapping a mould, moving it to another site or modifying it; check your own customer's requirements.

Mould acceptance

A new or modified mould is accepted before it enters series production. At acceptance, check at least:

On the day acceptance is signed, the mould card is opened, the starting counter is entered and the maintenance intervals are set.

Spare mould parts

The most common reason for long mould downtime is waiting for spare parts. Set a minimum stock per critical mould for wear and breakable parts such as ejector pins, bushes, slide gibs, hot runner heaters and thermocouples, O-ring sets and, on press tools, punches. IATF 16949 clause 8.5.1.5 (total productive maintenance) also requires availability of replacement parts for key manufacturing equipment and the packaging and preservation of equipment, tooling and gauging.

Link to mould change (SMED)

Tying interim cleaning to mould change is the easiest win: the mould is cleaned and checked as it comes off the machine and goes back on the rack as "ready for production". The last-shot sample of the removed mould shows whether service is needed. A mould with overdue service on the rack should not be scheduled for a mould change; otherwise a problem found during set-up multiplies the changeover time. Mould change and maintenance times are deducted from the machine's available capacity; I explained the calculation in the guide on capacity planning and machine load.

Common mistakes

  1. Recording parts as shots. A multi-cavity mould goes to service early and its life looks used up early.
  2. Tying service to the calendar. In a busy month the mould is serviced late, in a quiet month unnecessarily.
  3. Recording a repair as planned service. The counter is reset and the real service is skipped.
  4. Not knowing the expected life. The replacement decision is made when the mould breaks, and parts cannot be supplied for months.
  5. Not reporting damage to a customer-owned mould. A direct nonconformity in an audit.
  6. Forgetting inactive moulds. A spare-parts mould that runs once a year rusts on the rack; preservation is part of maintenance too.

What auditors ask

  1. Is your mould list up to date? Is the owner, status and location of every mould known?
  2. Are customer-owned moulds permanently marked?
  3. How were the service intervals set, and where is the shot counter read?
  4. Show me the last service record for this mould and the counter at that time.
  5. Has a customer-owned mould been damaged, and when was the customer informed?
  6. Is there a replacement plan for moulds approaching end of life?

Ask yourself

Free Excel template: Mould Maintenance and Tool Life Tracker

In the Mould List you enter the card, expected life and the interval of the three maintenance levels; from the Shot, Maintenance and Damage Logs the total counter, shots since last service, next service, shots left, estimated days, remaining life and status are calculated automatically. The dashboard filters by machine group and customer: moulds overdue and due for service, the 10 moulds with least life left, monthly maintenance count and hours, a Pareto of damage types and the latest damage records are on one page.

Download the Mould Maintenance and Tool Life Tracker (Excel, free). It comes with a fictitious example of 18 moulds; delete the sample data once you enter your own moulds.

As the number of moulds grows, it also matters whose signature drives acceptance, release to maintenance and end-of-life decisions. The Mould Acceptance and Maintenance section of the TAKMOS Maintenance Module runs these transitions with signed protocols and tracks wear part life from the shot counter.

Mould Maintenance and Tool Life Tracker

Total counter, shots left to next service, remaining life and status are calculated from the mould card and the shot, maintenance and damage logs. The dashboard filters by machine group and customer.

Download (Excel · 285 KB)
Maintenance Module · Mould Acceptance and Maintenance

See how we do this in the program on the module page, and try it in the demo.

Explore →
More from this area

All guides →