How to compare supplier quotations: RFQ, total cost of ownership (TCO) and weighted scoring
Hüseyin Şamlı · 2026-11-17 · 7 min read
Comparing supplier quotations is not a matter of listing the prices and picking the lowest. One quote is in euros, another in Turkish lira or US dollars; one has 30-day payment terms, another 90; one includes freight, another is ex works; one charges tooling separately, another has a minimum order quantity of 25,000 pieces. In this guide I explain step by step how to bring quotes to a common basis: requesting quotes against the same specification, exchange rate, payment terms, Incoterms, freight, tooling amortisation, MOQ and lead time; then total cost of ownership (TCO), weighted scoring, single-source risk and the decision record. A free Excel template for supplier quotation comparison is at the end.
1. Request quotes against the same specification (RFQ)
A good comparison starts with a good request for quotation (RFQ). If suppliers quote for different things, no calculation will make them comparable. Every RFQ should fix at least:
- Technical definition: drawing or specification number and revision, material, finish, tolerances, packaging and labelling requirements.
- Quantity: annual volume, typical order batch and project lifetime. If price depends on volume, ask for price breaks.
- Commercial terms: requested currency, Incoterm and place of delivery, expected payment terms, validity of the quote.
- Items to be quoted separately: one-off costs such as tooling, fixtures and test equipment; freight; samples and PPAP.
- Timeline: quote deadline, sample date, start of production and required first delivery.
If a supplier proposes a deviation from the specification (different material, different packaging), record it as an alternative quote; do not mix it into the main comparison.
2. Bring the price to a common basis
Currency and exchange rate
Convert all quotes into one currency. Use the rate on the decision date and record which rate you used. Currency risk is a separate issue: a price in a foreign currency carries a different risk from one in your own currency. Rather than mixing it into the price, reflect it in the risk score or in the decision note.
Payment terms: cash-equivalent price
A price of 100 at 90 days is cheaper than 100 paid immediately, because you keep the money for three more months. Discount the price to a cash equivalent with a simple formula:
Cash equivalent = unit price ÷ (1 + monthly financing rate × payment days ÷ 30)
At 0.5% per month, EUR 100 at 90 days is worth 100 ÷ 1.015 = EUR 98.52. In a high-interest currency at 3% per month, the same terms bring 100 down to 100 ÷ 1.09 = 91.74. Set the rate per currency; applying one rate to quotes in different currencies distorts the result. This simple-interest approach is enough for comparison; ask your finance team which rate to use.
Incoterms and freight
The Incoterm determines who pays for transport and customs. The ones you will meet most often in Incoterms 2020 are EXW, FCA, FOB, CIF, CPT, DAP and DDP. Roughly: under EXW you collect the goods at the supplier's door and bear almost all transport; under DAP the supplier delivers to the named place and import duties stay with you; under DDP the supplier bears those too. For the exact split of obligations, refer to the ICC publication. In practice: if the quote does not include delivery, estimate the freight, insurance, import duty and customs broker costs you will pay per unit and add them to the price.
Tooling and one-off costs
Spread tooling, fixture or test equipment cost over the product life: tooling amortisation = tooling cost ÷ (annual quantity × amortisation years). A quote with a low unit price but expensive tooling can cost more over the lifetime. Also ask in writing about tool ownership, maintenance, tool life (number of shots) and the handover of the tool if you change supplier.
MOQ and lead time
If the minimum order quantity (MOQ) is larger than your order batch, you carry the extra goods in stock. Approximate cost: average stock rises by (MOQ − batch) ÷ 2; divide the annual carrying cost of that stock by the annual volume. Include storage, counting and obsolescence risk in the carrying rate as well as financing. Judge lead time against the required date: a 70-day lead time is a problem for a project that needs parts in 60 days, whatever the price.
3. Total cost of ownership (TCO)
Adding these up gives the unit TCO:
TCO = cash-equivalent price + freight and duties + tooling amortisation + MOQ stock cost
Quality costs (incoming inspection, scrap, complaints), supplier development and first-sample costs can also be added; cover what you cannot measure in the quality and risk score. A sheet metal bracket example: 80,000 pcs per year, order batch 10,000, tooling amortised over 3 years, financing 0.5% per month, inventory carrying rate 2% per month:
| Item | Supplier A | Supplier B | Supplier C |
|---|---|---|---|
| Unit price (EUR) | 0.170 | 0.160 | 0.165 |
| Incoterm / payment terms | DAP / 90 days | EXW / 30 days | FCA / 60 days |
| Cash equivalent | 0.1675 | 0.1592 | 0.1634 |
| Freight + duties | 0 | 0.0120 | 0.0060 |
| Tooling (EUR) → amortisation | 9,000 → 0.0375 | 12,000 → 0.0500 | 7,500 → 0.0313 |
| MOQ → stock cost | 10,000 → 0 | 25,000 → 0.0036 | 10,000 → 0 |
| TCO (EUR/pc) | 0.2050 | 0.2248 | 0.2006 |
| Annual cost (EUR) | 16,399 | 17,984 | 16,049 |
B, the cheapest on the price list, is the most expensive in total cost. The lowest TCO is C.
4. Weighted scoring: price, quality, delivery, risk
The lowest TCO is not always the best decision. Add scores for quality, delivery and risk with weights fixed in advance. Example weights: price 50%, quality 20%, delivery 15%, risk 15%.
- Price score = 100 × lowest TCO ÷ the quote's TCO.
- Quality score: for existing suppliers from the supplier scorecard; for new ones from the pre-audit and sample results.
- Delivery score: whether the lead time fits the required date.
- Risk score: financial health, capacity, distance, single sourcing, currency risk.
In the example, quality scores are A 90, B 75, C 80; risk scores A 85, B 60, C 70; B's delivery score is 80, the others 100. Weighted scores: A 94.7, C 91.5, B 80.6. A costs EUR 350 a year more than C but offers better quality and lower risk. Accepting that difference is a decision and must be recorded with its reason. Set the weights before the quotes arrive; changing them afterwards means bending the calculation towards a desired result.
5. Single-source risk
If only one quote came in, or the part can be made by only one supplier, the decision is a risk decision whatever the price. Record it and write down the countermeasures: safety stock, tool ownership, a plan to develop a second source, a long-term agreement. Check the capacity side too; you can question whether the supplier can carry your volume with the same logic as in machine load calculation. If your company has a rule such as "at least three quotes", define who approves exceptions.
6. Decision record and approval
Keep a short decision record for every RFQ: the request, the quotes received, the comparison table, the recommended and the selected supplier, the reason if they differ, the decision date and the approver. Use an approval matrix that sets the approval level by value, and make sure the person who prepares the comparison is not the one who approves it. Give the unsuccessful suppliers short, objective feedback; it is the cheapest way to get better quotes next time.
The 6 most common mistakes
- Comparing quotes made against different specification revisions or different quantities.
- Looking at the unit price and missing payment terms, freight, tooling and MOQ.
- Correcting quotes in different currencies with one financing rate, or not recording the exchange rate.
- Setting the score weights after the quotes have arrived.
- Deciding on a single quote without recording it as a risk.
- Leaving a decision that differs from the recommendation without a reason.
What auditors and internal control ask
ISO 9001 clause 8.4.1 requires criteria for the evaluation and selection of external providers and retained records of these activities. IATF 16949 clause 8.4.1.2 requires a documented supplier selection process that considers, among other things, quality and delivery performance, risk and financial stability. Internal and customer auditors typically ask:
- Which criteria did you use to select this supplier? Were the criteria and weights fixed before the quotes arrived?
- How many quotes did you get? If only one, where are the reason and the approval?
- Did all suppliers quote against the same specification revision?
- Which exchange rate, payment terms and freight assumptions did you use?
- Who approved the decision, and what was the approval limit?
- If the cheapest quote was not chosen, why not?
Free Excel template
The Quotation Comparison template consists of the RFQs, Quotations and Comparison sheets. On RFQs you enter the request (item, specification, annual volume, batch, required date, reference price, decision and approval); on Quotations every quote (currency, price, Incoterm, freight, tooling, payment terms, MOQ, lead time, quality and risk score). The template calculates the unit cost converted to your currency and corrected for payment terms, the TCO, the weighted score, the rank, the recommended supplier and the gap to the cheapest quote; it flags single quotes, missing reasons and missing approvals. The Comparison sheet shows one RFQ with a decision form ready to sign. The Dashboard, filtered by category, shows savings, open RFQs and the supplier split. Sample data is fictitious.
Ask yourself
- Did all suppliers in your last RFQ quote against the same specification revision and the same quantity?
- Does your comparison include payment terms, freight, tooling and MOQ in the unit cost?
- Are your score weights written down and fixed before the quotes arrive?
- In how many of your last ten decisions did you have at least three quotes?
- Do you have a list of single-source items and a second-source plan?
- Can you find the reason and the approver for every decision that differs from the recommendation within a minute?
When Excel is no longer enough
As the number of RFQs and quotes grows and the same supplier quotes for many items, keeping the files up to date gets harder. In the Quotations section of the TAKMOS Purchasing Module, RFQs, incoming quotes and decision approval are kept in one record, and the selected quote turns directly into a purchase order.