How to build a supplier scorecard: ppm, OTD, A/B/C rating and IATF 16949 8.4.2.4
Hüseyin Şamlı · 2026-11-17 · 8 min read
In many plants, supplier evaluation is a form filled in once a year: purchasing ticks "good" in a few boxes and the form goes into a folder. Yet the damp resin that stops the line, the short-shipped connectors and the brackets flown in by express courier happen every month, and none of it shows up on that form. In this article I explain how to build a measurable supplier scorecard: which indicators, which formulas, how to weight them into an A/B/C rating, how to give suppliers feedback, and what IATF 16949 clause 8.4.2.4 expects you to monitor. There is a free Excel template at the end.
What does a supplier scorecard measure?
A scorecard measures supplier performance at regular intervals with the same rules every time. The aim is not to punish the supplier but to make problems visible in numbers and to make sure both sides look at the same data. Four areas are typical:
| Area | Indicator | Data source |
|---|---|---|
| Quality | ppm, rejected lots, number of 8Ds and closure time, disruptions in your plant | Incoming inspection and line nonconformity records |
| Delivery | On-time delivery (OTD), short/over deliveries, premium freight | Goods receipt records, order dates |
| Commercial | Price competitiveness, cost reduction proposals, payment and commercial terms | Purchasing review |
| Cooperation | Responsiveness, document discipline (PPAP, certificates), change notification | Purchasing and quality review |
Quality and delivery should be calculated automatically from recorded data. Commercial and cooperation can be rated once a quarter with a 1–5 score given by a few people. What matters is that the basis of every score is written down.
Quality indicators: ppm, rejected lots and 8D
ppm (parts per million) is the rejected quantity divided by the received quantity in the period: ppm = rejected parts / received parts × 1,000,000. Example: 40,000 clips were received in a month and 12 were rejected at incoming inspection and on the line; ppm = 12 / 40,000 × 1,000,000 = 300. Count supplier-caused defects found on the line and at the customer as well, not only at incoming inspection; otherwise escaped defects never appear on the scorecard.
ppm is not meaningful for every material. For bulk materials such as resin, paint or chemicals, the rejected lot rate (rejected lots / received lots) is a better indicator. For low-volume, expensive parts a single reject inflates ppm; read ppm for these suppliers over 3 or 6 months.
The number of 8Ds and their closure time show how the supplier solves problems. The same defect coming back, or an 8D closed late or superficially, is a stronger warning than ppm. I explain what to expect from an 8D in How to write an 8D report; read the supplier's report against the same criteria.
Delivery indicators: OTD, short and over deliveries
OTD (on-time delivery) is the share of delivery lines delivered on time. Define "on time" in advance: for example, no more than 3 days before the requested date and not late at all. Early deliveries also fill the warehouse and disturb the plan, so both sides of the window need a definition. Quantity accuracy is measured separately: a delivery that differs from the ordered quantity by more than ±5% counts as short or over. Also count premium freight (express transport paid to recover a delay) and line stops caused by deliveries separately, because they are direct costs.
Weighted score and A/B/C rating
Each area is converted into a 0–100 score and then combined with weights. An example rule:
- Quality score (40%): 100 if ppm is at or below target (e.g. 150), 0 at or above the zero-score limit (e.g. 1500), linear in between. Deduct 10 points for every 8D opened in the period and 20 for every disruption.
- Delivery score (30%): 100 if OTD is 95% or higher, 0 at 75% or lower, linear in between. Deduct 5 points for every short/over delivery and 10 for every premium freight.
- Commercial score (15%) and cooperation score (15%): average of the 1–5 scores from the quarterly review × 20.
Example: a supplier's month shows ppm 300 (quality score 88.9), one 8D (−10 → 78.9), OTD 90% (delivery score 75), commercial 80, cooperation 70. Total = 0.40 × 78.9 + 0.30 × 75 + 0.15 × 80 + 0.15 × 70 = 76.6. With thresholds A ≥ 85, B ≥ 70, C < 70, this supplier is B-rated.
Weights and thresholds are not given in the standard; you set them in your own procedure. If your product contains safety or regulatory critical parts, give quality more weight. Rate suppliers on the average of the last 3 months rather than a single month: one bad month should not push a supplier to C, but an ongoing problem should not be hidden either.
Monthly measurement, quarterly review
A rhythm that works in practice: quality and delivery indicators are calculated every month and sent to suppliers at the start of the following month. Once a quarter, purchasing, quality and logistics sit together, give the commercial and cooperation scores, confirm the rating and decide on development actions. With critical suppliers this meeting is held in person or by video; for the others the scorecard and a short note are enough.
Supplier feedback and development plan
A scorecard that is never sent to the supplier is only half the job. The feedback should contain:
- The indicators, targets and the supplier's values for the period, with the calculation rule written out.
- A concrete example for every off-target indicator: which lot, which date, which defect.
- The expected action and due date: root cause analysis, containment, permanent correction.
- For C-rated suppliers, a written development plan: owner, due date, measurable target (e.g. "ppm < 300 within 3 months").
Development actions often go down to the supplier's own process: updated PFMEA and control plan, end-of-line checks, poka-yoke. You will find what to look for when you ask a supplier for an updated control plan in How to prepare a control plan. Write down as a rule that C-rated suppliers receive no new business and that alternative sources are sought.
What does IATF 16949 require?
ISO 9001 clause 8.4.1 requires criteria for the evaluation, selection, monitoring of performance and re-evaluation of external providers, and records of these activities. IATF 16949 clause 8.4.2.4 (supplier monitoring) makes this automotive-specific: there must be a documented process and criteria to evaluate supplier performance, and at least the following indicators are monitored:
- conformity of delivered product to requirements,
- disruptions at the receiving plant (including yard holds and stop ships),
- delivery schedule performance,
- number of premium freight occurrences.
If your customer provides them, special status notifications related to quality or delivery, and dealer returns, warranty, field actions and recalls are added to the monitoring. Clause 8.4.2.5 (supplier development) asks you to determine the priority, type and timing of development actions based on these monitoring results, second-party audit findings, certification status and risk analysis. In other words, the scorecard is the input to the development plan.
Common mistakes
- Recording only problem deliveries; the denominator of OTD and ppm is incomplete and the rates become meaningless.
- Leaving supplier defects found on the line and at the customer off the scorecard.
- Not counting premium freight and disruptions in your plant at all.
- Calculating the scorecard but never sending it to the supplier.
- Not opening a development plan for a C-rated supplier, or not following it up.
- Changing the weights and the "on time" definition every period, so trends can no longer be compared.
What auditors ask
- Where are your supplier performance evaluation process and criteria documented?
- How do you monitor the four indicators of 8.4.2.4? Do you have a record of premium freight?
- Show me this supplier's score for the last quarter and the records behind it.
- What feedback did you give to a poor performer, and where is the development plan?
- Was a special status or field issue from your customer reflected in the supplier evaluation?
- On what basis did you set development priorities?
Ask yourself
- Do I record every delivery with its requested and actual date?
- Could I name last month's three worst suppliers within a minute?
- How many times did we pay premium freight this year, and because of which suppliers?
- Do my suppliers receive their scorecards monthly or quarterly?
- How many of my open 8Ds are past the target time?
- Do I have a development plan with due dates for every C-rated supplier?
Free Excel template
The Supplier Scorecard template has four data sheets: the supplier list (category, criticality, certificate, approval status), deliveries (requested and actual date, ordered and delivered quantity, premium freight, disruption), the quality log (rejected quantity, disposition, rejected lot, disruption, 8D opening and closing) and the quarterly commercial/cooperation review (feedback and development action). ppm, OTD, quality and delivery scores, the weighted total score and the A/B/C rating are calculated automatically; targets, penalty points, weights and rating thresholds are changed on the Lists sheet. The Dashboard, filtered by material category and period, shows ppm and OTD trends, the supplier ranking, C-rated and off-target suppliers, and open 8Ds. Sample data is fictitious.
When Excel is not enough
As the number of suppliers grows, and deliveries are recorded at goods receipt while nonconformities are logged by quality, feeding the scorecard by hand gets hard. In the Supplier Management section of the TAKMOS Purchasing Module, the scorecard is calculated directly from goods receipt and quality records, and development actions are tracked on the supplier card.