Capacity planning: how to calculate machine load (with injection moulding and assembly examples)
Hüseyin Şamlı · 2026-11-09 · 7 min read
Capacity planning means comparing the demand of the coming weeks with the time your machines and lines can actually produce. The question is simple: "Which machine cannot keep up this week, and which one is idle?" The answer rests on three numbers: available time, net capacity and required time. In this guide I explain step by step how to calculate machine load, using an injection moulding machine and an assembly line as examples; I also cover finding the bottleneck, which remedy to use when a machine is overloaded, and the rolling 12-week view. A free Excel template is at the end.
1. Work out the available time
The calculation starts with the calendar. For each week, write down the gross time first, then what has to be deducted:
- Gross time = working days × shifts per day × shift length. Take the shift length net of breaks: an 8-hour shift with a 30-minute break is 7.5 hours.
- Calendar losses: public holidays, half days, year-end stocktake, plant shutdown. A holiday week may have 3.5 working days instead of 5.
- Planned stops: preventive maintenance, weekly meetings, cleaning. Take them from your preventive maintenance plan; the maintenance calendar and the capacity calendar should show the same week.
- Extra time: add planned Saturday overtime or an extra shift for that week.
Available time = gross time − calendar losses − planned stops + extra time. This is the time the machine is planned to produce.
2. Calculate net capacity: the OEE factor
A machine does not make good parts for all of its available time. Breakdowns, mould changes, speed losses and scrap take part of it. The most practical way to reflect this loss in the plan is to use the machine's actual OEE as a factor:
Net capacity (hours) = available time × OEE factor
Use the measured average OEE of the last 3–6 months; I explain how to calculate OEE in the OEE guide. Watch two points. First, if you have already deducted planned stops, the availability part of OEE must not include them; do not count the same loss twice. Second, apply OEE either to capacity or to demand, not to both. If no measured value exists, start with 75–85% and update it with data. If you add mould change time separately (below), choose the factor accordingly; otherwise the change-over loss is deducted twice.
3. Calculate required time: cycle time, cavities, demand
Convert the weekly demand of each part into machine hours:
Required time (hours) = quantity × cycle time (s) ÷ number of cavities ÷ 3,600 + mould / set-up change time
In injection moulding, the number of cavities is the number of parts per shot: a 2-cavity mould on a 48-second cycle means 24 seconds per part. In assembly, the equivalent is parts per cycle, which is 1 on most lines. Take the cycle time measured on the shop floor, not the value from a catalogue or quotation.
4. Calculate machine load
Load (%) = required time ÷ net capacity × 100
Calculate load for each machine and each week separately. A monthly average hides weekly peaks: a machine with an 85% monthly average can be 120% loaded in a holiday week.
Example 1: Injection moulding machine (350 t)
| Item | Calculation | Result |
|---|---|---|
| Gross time | 5 days × 3 shifts × 7.5 h | 112.5 h |
| Planned maintenance | weekly | − 4 h |
| Available time | 112.5 − 4 | 108.5 h |
| Net capacity | 108.5 × 0.80 (OEE factor) | 86.8 h |
| Support bracket | 10,000 pcs × 48 s ÷ 2 cavities ÷ 3,600 + 1.5 h mould change | 68.2 h |
| Front panel | 1,400 pcs × 55 s ÷ 1 cavity ÷ 3,600 + 1.5 h mould change | 22.9 h |
| Load | (68.2 + 22.9) ÷ 86.8 | 105% |
The machine is overloaded by 4.3 hours that week. One Saturday of overtime adds 3 × 7.5 × 0.80 = 18 hours of net capacity, which closes the gap.
Example 2: Assembly line
Take a three-station assembly line with station times of 32, 38 and 42 seconds. The slowest station sets the line cycle: 42 seconds. The line runs 2 shifts: 5 × 2 × 7.5 = 75 hours, minus 2 hours of planned stops = 73 hours, and with an OEE factor of 0.82 the net capacity is 59.9 hours. A weekly demand of 4,800 pcs needs 4,800 × 42 ÷ 3,600 = 56 hours; the load is 94%. In assembly, capacity depends on people as well as equipment: if the line runs short of operators, stations are combined and the cycle gets longer. Write down in the plan which cycle is achieved with how many people.
5. Find the bottleneck
The bottleneck is the resource with the highest load, the one that limits the output of the plant. If a part goes from moulding to welding and leak testing, the chain runs at the speed of its slowest link. An hour gained on a non-bottleneck machine adds nothing to output; an hour lost at the bottleneck is lost for the whole plant. So:
- Plan maintenance, mould changes and break cover on the bottleneck machine most carefully.
- Keep a small buffer stock in front of the bottleneck so that it never waits.
- Scrap at the bottleneck is the most expensive scrap; put first-off approval and quality checks before it.
The bottleneck is not fixed; it moves as the product mix changes. Look at the weekly load table again every week.
6. Read the weekly load percentage
Colour the machine × week table; problem weeks show at a glance. A commonly used split in practice:
| Load | Meaning | Action |
|---|---|---|
| Up to 85% | Margin for breakdowns, scrap and rush orders | Run the plan; free capacity can be offered to sales or used to build ahead |
| 85–100% | Little margin, a small breakdown will hurt | Monitor; prepare a remedy in advance |
| Above 100% | Demand cannot be met with this capacity | Activate a remedy or renegotiate the date |
The thresholds depend on your sector and on how reliably OEE is measured; set them from your own experience.
7. Check mould–machine compatibility
A mould cannot be moved to a machine just because the machine looks free. In injection moulding, check the following before choosing an alternative machine:
- Does the clamping force (tonnage) meet the part's requirement?
- Does the mould fit between the tie bars, and are mould height and opening stroke sufficient?
- Are screw diameter and shot volume suitable for the part weight?
- Does the machine have the hot-runner zones, core pulls and cooling connections the mould needs?
- Are the robot and gripper compatible?
Keep compatibility in a matrix and use an alternative machine only for moulds that have been trialled and approved on it. In automotive, producing a part on another machine may require customer approval or notification; check your customer-specific requirements. In assembly, the same logic applies to fixtures, test programs and operator qualification.
8. What to do when a machine is overloaded
Try the remedies in order of cost and speed:
- Overtime / Saturday: the quickest remedy for short, small overloads. Calculate the net hours one extra day brings and compare them with the gap; a permanent overtime plan is a sign of a capacity problem.
- Extra shift: if the machine runs fewer than 3 shifts. Plan staffing and skills at the same time.
- Alternative machine: if there is an approved mould and a suitable machine. The cycle on the alternative machine may differ; recalculate the required time with that cycle.
- Build ahead: produce to stock in weeks with free capacity. Consider stock cost and shelf life.
- Subcontract: have another manufacturer produce the part. It requires quality approval and logistics lead time.
- Renegotiate the date: the last resort; talk to the customer early and with figures.
At the same time, list the actions that raise capacity permanently: cycle time reduction, shorter mould changes (SMED), fewer breakdowns. Every minute gained at the bottleneck is direct output.
9. The rolling 12-week view
A capacity plan is not made once and filed away. At the start of each week the plan moves one week forward: last week drops off, a new week is added and demand is updated with customer call-offs. Twelve weeks is usually long enough to set up an extra shift, hire people or arrange subcontracting. The first 1–2 weeks are almost fixed and hard to change; later weeks are based on forecasts and can be planned more roughly. Look at the same table in the weekly production meeting: which machine is overloaded, in which week, which remedy, who is responsible.
The 6 most common mistakes
- Forgetting to divide the cycle time by the number of cavities, or using the theoretical cycle.
- Applying OEE to both capacity and demand, or not applying it at all.
- Ignoring holidays, maintenance shutdowns and mould changes.
- Looking at the monthly average and missing weekly peaks.
- Counting an idle machine as an alternative without checking mould compatibility.
- Making the plan once and never updating it; demand changes and the plan goes stale.
What auditors and customers ask
IATF 16949 clause 8.2.3.1.3 requires the manufacturing feasibility of a new product or process to be analysed, including the capacity requirements specified by the customer; the contingency plans of clause 6.1.2.3 also cover capacity losses such as key equipment failures. Auditors and customer quality representatives typically ask:
- On which machine, with which cycle time and OEE assumption, do you meet the weekly demand for this part?
- When was your capacity calculation last updated? Does it include the latest demand increase?
- Which machine is your bottleneck, and what do you do if it breaks down?
- Is the alternative machine approved, and where is the evidence?
- Is there a gap between the OEE you planned and the OEE you achieved?
Free Excel template
The Weekly Capacity Plan template has Machines, Parts, Demand and Calendar sheets. For each machine you enter the shift pattern, planned stops and OEE factor; for each part the primary and alternative machine, cycle time, cavities and required tonnage; for demand the quantities of 12 weeks. The template calculates net capacity, required hours and machine × week load, and flags mould–machine tonnage compatibility. The Dashboard, filtered by line / machine group, shows the bottleneck, overloaded weeks and free capacity. The sample data is fictitious.
Ask yourself
- Can you name this week's most loaded machine and its load percentage within a minute?
- Are the cycle times in your capacity calculation measured on the shop floor?
- Is your OEE factor based on actual data from the last three months?
- Are holidays and maintenance shutdowns in your capacity calendar?
- Do you have an approved alternative machine for every mould on your bottleneck machine?
- Do you update your plan every week and look at least 8–12 weeks ahead?
When Excel is no longer enough
As the number of machines and parts grows and demand changes daily with customer call-offs, keeping a spreadsheet up to date becomes hard. In the Orders and Capacity section of the TAKMOS Planning Module, sales orders turn directly into machine load; the bottleneck and overloaded weeks show as soon as an order is entered.