MRP explained: material requirements planning step by step (BOM, net requirements, order week)
Hüseyin Şamlı · 2026-11-17 · 8 min read
MRP (material requirements planning) starts from customer demand and tells you which material to order, how much and in which week. The method has not changed for decades: you explode the bill of materials, find the gross requirement, deduct stock on hand and orders already on the way, round the remainder to the lot rule and offset it by the lead time. The problem is rarely the formula; it is the accuracy of the inputs. In this guide I walk through MRP step by step for an automotive supplier with injection moulding and assembly, including a worked example. A free Excel template is at the end.
1. What inputs does MRP need?
MRP has five inputs. If one is missing or wrong, so is the output:
- Demand (master production schedule): weekly quantities per finished good, from customer call-offs (EDI) and forecast. Deduct finished-goods stock from this demand first; the remainder is that week's net production.
- Bill of materials (BOM): how much of each component one finished good needs.
- Stock on hand: usable, quality-released stock. Quarantined or blocked stock does not count.
- Open orders: purchase orders and production orders placed but not yet received, with the expected delivery week.
- Material parameters: safety stock, minimum order quantity (MOQ), pack size and lead time.
2. Explode the bill of materials
BOM explosion breaks finished-goods demand down to every component in the structure. In a plant with moulding and assembly the BOM usually has two levels:
- Level 0 – finished good: for example a centre console lid (assembly).
- Level 1 – components: moulded parts you make yourself (semi-finished), bought-in springs, screws, felt, packaging and labels.
- Level 2 – raw material: the resin and colour masterbatch of the moulded part.
For resin, enter the quantity per in kg as part weight + runner weight. A hot-runner mould has no runner; if a cold runner is reground and reused, account for that separately. Entering one resin in grams and another in kg is the most common mistake: the requirement comes out a thousand times wrong.
Levels matter because the component of a semi-finished item is needed in the week the semi-finished item is produced, not in the week the finished good is assembled. The semi-finished item is netted first against its own stock and open production orders; only if a requirement remains does a resin requirement arise.
3. Add the scrap allowance correctly
The scrap allowance adds the expected loss on a component to the requirement. Two formulas are common:
- Quantity per ÷ (1 − scrap %): correct when the scrap rate is the share of input material that is lost.
- Quantity per × (1 + scrap %): close at low rates but slightly understates the requirement.
At 3% scrap the difference is small (1.0309 versus 1.03). At 10% it grows: 1.111 versus 1.10. Take the scrap rate from measured data, not from estimates; I explain how to see which part scraps how much in the scrap tracking and Pareto guide. Add scrap in one place only: if you add it both to the BOM and to the demand, it is counted twice.
Example: 3,000 console lid bodies are to be moulded in a week. Part + runner weight is 0.185 kg, resin scrap 3%. Gross resin requirement = 3,000 × 0.185 ÷ 0.97 = 572.2 kg.
4. From gross to net requirement
For each material, the following is calculated in weekly buckets:
Available = previous week's stock + scheduled receipts − gross requirement
Net requirement = safety stock − available (only when available falls below safety stock)
If you plan to protect safety stock, the net requirement arises in the week stock drops below the safety level. Some companies set safety stock to zero and treat only negative stock as a requirement; write down which rule you use.
5. Lot sizing: MOQ and pack size
The net requirement is not the order quantity yet. It is raised to the supplier's minimum order quantity and rounded up to the pack size:
Planned order = MOQ if the net requirement is below MOQ; then round up to a multiple of the pack size
Resin comes in 25 kg bags or 1,000 kg big bags; screws in boxes of 5,000; electronic boards on reels or trays of 250. A net requirement of 150 kg with an MOQ of 1,000 kg becomes an order of 1,000 kg, and the surplus stays in stock. For a semi-finished item the MOQ is the smallest production batch that justifies the mould set-up. MOQ and pack size drive your stock level directly; review them with the supplier once a year.
6. Order release week from lead time
Once the week the material must arrive is known, the order release week is moved back by the lead time (lead-time offset):
Order release week = required (delivery) week − lead time
If the release week falls before today, the order is overdue: even if placed today it will not arrive on time. In that case, agree expediting, a split delivery or premium freight with the supplier. Include the supplier's production time, transport, customs and your own goods-in inspection in the lead time. For an electronic board from the Far East, 10–14 weeks is normal.
Worked example: PP resin
Stock on hand 2,100 kg, safety stock 1,000 kg, MOQ 1,000 kg, pack size 25 kg, lead time 3 weeks. An open order of 2,000 kg arrives in week 2.
| Week | 1 | 2 | 3 | 4 | 5 | 6 |
|---|---|---|---|---|---|---|
| Gross requirement (kg) | 600 | 700 | 650 | 600 | 700 | 650 |
| Scheduled receipts | – | 2,000 | – | – | – | – |
| Projected stock | 1,500 | 2,800 | 2,150 | 1,550 | 1,850 | 1,200 |
| Net requirement | – | – | – | – | 150 | – |
| Planned order receipt | – | – | – | – | 1,000 | – |
| Planned order release | – | 1,000 | – | – | – | – |
In week 5 available stock falls to 1,550 − 700 = 850 kg, 150 kg below safety stock. The net requirement is 150 kg; because of the MOQ the order is 1,000 kg. With a 3-week lead time, the order must be placed in week 2 at the latest.
7. Weekly buckets and a rolling plan
Automotive call-offs usually arrive weekly, so a weekly bucket is a practical resolution. The horizon should be at least as long as the longest lead time; 12 weeks is enough for most materials. The plan is rerun every week: last week drops off, a new week is added, demand and open orders are updated. Demand falls in New Year and holiday weeks; reflect that in the demand. Material planning and machine capacity should be fed from the same demand; I cover the capacity side in the capacity planning guide.
The 6 most common mistakes
- Mixing units in the BOM (g and kg, pieces and boxes).
- Adding scrap both to the BOM and to the demand, or not at all.
- Not deducting received quantities from open orders, so the same material is counted twice.
- Counting quarantined or nonconforming stock as available.
- Taking only the supplier's production time as lead time and forgetting transport and goods-in inspection.
- Running the plan once a month while demand changes weekly; the proposals go stale.
What auditors and customers ask
IATF 16949 clause 8.5.4.1 requires an inventory management system to optimise inventory turns and stock rotation such as FIFO. Clause 8.4.2.4 includes delivery schedule performance and the number of premium freight occurrences in supplier monitoring. Many automotive customers also ask for a Global MMOG/LE self-assessment. Auditors typically ask:
- From which demand data, and how often, do you calculate material requirements?
- When were your BOM and scrap rates last updated, and who approved them?
- How were safety stock and MOQ values set?
- How many premium freight shipments did you have in the last three months, and why?
- How do you monitor slow-moving and obsolete-revision stock?
Free Excel template
The MRP – Material Requirements Plan template has Demand, Bill of Materials, Materials and Open Orders sheets. You enter finished-goods demand in 12 weekly buckets; the template explodes a two-level BOM, adds the scrap allowance, finds the net requirement, rounds planned orders to MOQ and pack size and sets the release week from the lead time. The MRP Table shows each material week by week. The dashboard, filtered by material group and supplier, shows the orders to place this week, critical materials, the stock-out week and order value by supplier. Sample data is fictitious.
Ask yourself
- Can you see in one list which materials must be ordered this week?
- Are the resin quantities in your BOM based on measured part + runner weights?
- Do your scrap rates come from the last three months of real data?
- Do your lead times include transport and goods-in inspection?
- Is your open-order list up to date with received quantities?
- Do you run the plan every week and see at least as far ahead as your longest lead time?
When Excel is no longer enough
Once materials run into the hundreds, BOM lines into the thousands and demand changes daily with customer call-offs, keeping an Excel file current becomes hard. In the Material Requirements section of the TAKMOS Planning Module, customer orders turn directly into material requirements through the BOM; materials to order and late deliveries appear on the same screen.