Material Requirements
Gross requirement is order quantity multiplied by the unit consumption in the bill of materials. Net requirement is found by deducting available stock in Logistics and the remaining quantity of open purchase orders in Purchasing. The order week is brought forward by the supplier lead time and quantities below MOQ are rounded up; selected proposals go to Purchasing as a single purchase requisition.
From requirement to purchase requisition
Open proposals are transferred to the Purchasing Forecast with the hourly publish.
Main screens of the section


Links to other sections and modules
- LogisticsAvailable raw material stock is deducted from net requirements
- PurchasingThe remainder of open purchase orders counts as in transit; proposals become STs, supplier lead time and price summary are read
- ProjectBill of materials (BOM) and material factors
- 04 Revenue and İMMProposals and the bill of materials feed planned İMM
Guides, templates and features
Frequently asked questions
How is net requirement calculated?
Available stock in Logistics and the unreceived remainder of sent, confirmed or partially delivered purchase orders in Purchasing are deducted from the gross requirement. The remaining quantity is the net requirement.
How does a proposal become a requisition?
On the Order Proposals page, proposals are selected and converted; they are all combined into a single purchase requisition (ST), with one line per proposal. The approval chain and number of quotations are set by the amount rules in Purchasing settings.
Can a proposal that has become a requisition be changed?
No. A proposal with requisition or order status cannot be changed in Planning; the requisition proceeds in Purchasing.