TAKMOSPRODUCTION ERP
Excel templates FREE Try the demo
Home › Guides › How to calculate OEE: availability, performance and quality, with a worked example
Production

How to calculate OEE: availability, performance and quality, with a worked example

Hüseyin Şamlı · 2026-11-08 · 7 min read

OEE (Overall Equipment Effectiveness) shows, as a single percentage, how much of your planned production time actually turned into good parts. The calculation is simple, but it is also easy to get wrong: the wrong cycle time, rework counted as good or planned downtime mixed in can move the result by 10–15 points. In this guide I explain the three OEE factors, a step-by-step worked example, the six big losses and the most common mistakes; at the end there is a free Excel template that calculates OEE automatically from a shift log.

The OEE formula

OEE is the product of three ratios:

OEE = Availability (A) × Performance (P) × Quality (Q)

You can reach the same result with a single formula: OEE = (ideal cycle time × good count) / planned production time. This shortcut is a good check that the three ratios were calculated correctly.

Split the time correctly first

The OEE denominator is not the shift time but the planned production time. Planned downtime such as breaks, meals, planned maintenance and time not scheduled because there are no orders is deducted at the start; it is not an OEE loss. Time breaks down like this:

  1. Shift time − planned downtime = planned production time
  2. Planned production time − unplanned stops (breakdowns, changeovers, waiting for material) = run time
  3. Run time − speed losses and minor stops = net run time (ideal cycle × total count)
  4. Net run time − time spent on defective parts = fully productive time (ideal cycle × good count)

Minor stops (in most plants, interruptions shorter than 5 minutes) are not deducted from run time; because they are hard to log one by one, they show up inside the performance loss. Define the threshold in writing for your plant and apply the same rule on every line.

Worked example: one shift on an injection moulding line

InputValue
Shift time480 min
Planned downtime (breaks, meal, cleaning)50 min
Breakdown25 min
Mould change and adjustment35 min
Ideal cycle time30 s/part
Total count640 parts
Scrap + rework + start-up scrap12 + 8 + 6 = 26 parts

Step by step:

Check: 614 × 30 s = 307 min; 307 / 430 = 71.4%. If both routes give the same answer, the calculation is right. Converting losses to minutes makes the picture even clearer: 60 min availability loss, 50 min performance loss, 13 min quality loss. Where to start improving on this shift is no longer a matter of opinion.

The six big losses

The TPM approach groups losses under six headings. If every stop and defect is coded to one of them, OEE stops being just a number and becomes a loss Pareto:

FactorLossExample
Availability1. BreakdownsMechanical, electrical or mould failure
Availability2. Setup and adjustmentsMould/product changeover, waiting for first-part approval
Performance3. Idling and minor stopsPart jams, sensor resets
Performance4. Reduced speedRunning the machine slower than the ideal cycle
Quality5. Process defectsScrap and rework in stable production
Quality6. Start-up lossesScrap after start-up and after changeovers

Waiting for material, operators or energy is not one of the six; most plants record it as "other unplanned stops" under availability. Whichever way you choose, write it down and keep it stable, or month-to-month comparisons lose their meaning.

How do you set the ideal cycle time?

The accuracy of the performance ratio depends entirely on the ideal cycle time. The ideal cycle is the design rate of the machine or line, or the proven best sustainable cycle. It is not the standard time used in planning; standard times usually include an allowance for losses. For a multi-cavity mould, the ideal time per part is the cycle time divided by the number of cavities. The ideal cycle changes with the product, so record the ideal cycle for that product on every row of the shift log.

What does 85% "world class" mean?

85% OEE is a commonly cited reference that comes from Seiichi Nakajima's TPM work: roughly 90% availability × 95% performance × 99.9% quality. It is not a rule or a requirement of any standard. Holding a high-mix line with frequent mould changes to the same target as a single-product line is misleading. Set your target from your own baseline and watch the trend; a line that moves from 55% to 65% is doing better work than one standing still at 80%.

OEE vs TEEP

OEE measures effectiveness within planned production time. TEEP (Total Effective Equipment Performance) looks at all calendar time: TEEP = OEE × utilisation, where utilisation = planned production time / calendar time. A line running 2 shifts, 5 days a week with 71% OEE has a TEEP of about 30%. OEE answers "how good are we while we run?", TEEP answers "how much of the available capacity do we use?". Look at TEEP too when a new machine investment is on the table.

Most common mistakes

What auditors ask

IATF 16949 clause 8.5.1.5 (total productive maintenance) requires maintenance objectives to be set and monitored; OEE is the most common example of such an objective. Typical auditor questions:

  1. How is OEE calculated and are the definitions written down? What counts as planned downtime?
  2. Where do the ideal cycle times come from and who approved them?
  3. Which actions were opened for lines below target, and what were the results?
  4. Is there a root cause analysis for the top item on the loss Pareto?

Free Excel template: OEE and Shift Log

In the OEE and Shift Log template you enter one row per line and shift: planned time, planned and unplanned stops (breakdown, setup/adjustment, other), minor stops, ideal cycle, total count, scrap, rework and start-up scrap. A, P, Q and OEE are calculated for each row; if P exceeds 100% the Check column flags it. The Dashboard shows overall OEE, line and shift comparison, the loss Pareto and an 8-week trend, filtered by line, shift and date; the Loss Tree sheet converts the time model and the six big losses into minutes. Sample data is fictitious.

When Excel is no longer enough

As the number of lines grows, adding up minutes by hand at the end of each shift becomes slow and error-prone. The Performance and Meetings section of the TAKMOS Production Module calculates OEE from shop-floor shift and downtime records, ranks losses by reason code in a Pareto and prepares Tier meeting agendas from the same data.

OEE and Shift Log

Availability, performance, quality and OEE calculated from one row per shift; line, shift and loss Pareto on the dashboard.

Download (Excel · 271 KB)
Production Module · Performance and Meetings

See how we do this in the program on the module page, and try it in the demo.

Explore →
More from this area

All guides →