How to run tier and morning (Asakai) meetings: a 15-minute shop-floor routine
Hüseyin Şamlı · 2026-11-09 · 8 min read
The morning meeting is the most frequent and least productive meeting in a plant. Everyone stands, yet it takes 40 minutes; the shift report is read out, nobody decides, and yesterday's problem is discussed again tomorrow. A tier meeting system (asakai, Japanese for "morning meeting") turns this around: short, at the same time, in front of the same board, at the lowest level where the problem can be solved. Anything that cannot be solved moves up a tier within a set time. In this guide I explain the tiers, the SQDCP board, the 15-minute agenda, escalation rules, action tracking and how to start the system in 4 weeks. At the end there is a free Excel tier board template.
Tier levels: who, where, when?
The tier system orders meetings by organisational level. Each tier uses the output of the one below, so the times are set up as a chain.
| Tier | Participants | Place and time | Length | Focus |
|---|---|---|---|---|
| Tier 1 · line | Line leader, operators; quality and maintenance technician if needed | Line board, start of shift | 10–15 min | What happened yesterday, what blocks us today, who does what |
| Tier 2 · area | Area / production supervisor, Tier 1 leaders, quality, maintenance, planning | Area board, 30–45 min after Tier 1 | 15 min | Reds from the lines, topics needing support |
| Tier 3 · plant | Plant manager, department heads | Plant board, after Tier 2 | 15–20 min | Topics needing customer, safety or resource decisions |
Large sites may add Tier 4 (general manager, several plants). In a small company Tier 2 and Tier 3 can be merged; what matters is not the number of tiers but having it in writing where a topic goes and within how long.
The SQDCP board: five letters, one colour per day
The backbone of the board is SQDCP: Safety, Quality, Delivery, Cost, People. Some plants write SQCDP or add E (environment) or M (morale). Each letter has a calendar of the days of the month; each day is coloured green or red against a criterion.
- S: red if there is an accident, a first-aid case or a near miss that has not been closed.
- Q: red if in-line scrap is above target, or there is a customer complaint or quality alert.
- D: red if schedule attainment is below 95% or a shipment is late.
- C: red if there is unplanned overtime, premium freight or scrap cost above target.
- P: red if absenteeism exceeds the threshold or an unqualified operator is on a station.
The rule is simple: the criterion must be measurable and known before the meeting. "Quality was poor" is not a criterion; "in-line scrap above 1.5%" is. I explain how to calculate scrap rate and cost for Q and C in the scrap tracking and Pareto guide, and the losses behind the D letter in the OEE guide. Next to the calendar there is a small trend chart and an open action list for each letter.
The 15-minute agenda
The agenda protects the time. A sample Tier 1 flow:
| Minute | Step | What happens |
|---|---|---|
| 0–2 | Safety | Yesterday's incident, near misses, today's risk (mould change, maintenance work). The S letter is coloured. |
| 2–7 | Q, D, C, P | Yesterday's result for each letter: green or red? If red, the reason in one sentence. |
| 7–11 | Actions | Open actions are reviewed by due date; new reds get an owner and a due date. |
| 11–13 | Today's plan | Target quantity, missing people, material and equipment risks. |
| 13–15 | Escalation | Topics the line cannot solve are written up for Tier 2; it is clear who takes them. |
Root cause analysis is not done in the meeting. The meeting makes the problem visible, gives it an owner and a deadline; the analysis is done afterwards, on the shop floor, with the right people.
Standing, in front of the board
A tier meeting is held standing in front of the board. Chairs make it longer; a screen leaves the talking to one person. The board should be next to the line so that people can walk to the part, station or mould while the problem is discussed. A calendar coloured by hand increases operator ownership; even with a digital board, the line leader should enter the data in the meeting.
Escalation rules: what goes up, and within how long?
The value of a tier system lies in escalation. Without written rules, either everything stays on the line or everything goes to the manager. A sample rule set:
- Tier 1 → Tier 2: topics not solved on the line within 24 hours; topics needing support from another department (maintenance, quality, planning) or authority; the same red repeating three days in a row.
- Tier 2 → Tier 3: topics not solved within 48 hours; topics affecting several areas; topics needing a budget, investment or headcount decision.
- Straight to Tier 3 (same day): accidents, defects that reached the customer, shipment stops.
Escalation is a request for help, not blame. The upper tier does not take over the topic; it removes the obstacle and carries the answer back down: the decision taken at Tier 2 is announced at Tier 1 the next day. Without this return path, line leaders stop escalating after a while.
Action tracking: no action without an owner and a date
Every red is linked to an action row. The row needs at least:
- Number and opening date
- Line and letter (S, Q, D, C, P)
- Topic and the work to be done (one sentence starting with a verb)
- A single owner (a person, not a department)
- Due date
- Status and closing date
- Escalation tier and date
The open action list is read at every meeting, starting with the oldest due date. An overdue action has two options: a new due date with a reason, or escalation to the next tier. If the quality problem is large, the action row is linked to an 8D report; only its number stays on the board.
Visual status: green and red days
Anyone looking at the board should understand the status in five seconds. For that:
- Each letter shows the days of the month in green or red; if there is no record, the day stays blank, not green.
- At month end, the green-day rate is calculated per letter: green days ÷ (green + red days). Example: if Q was green on 18 of 21 recorded days, the rate is 86%.
- On Tier 2 and Tier 3 boards a day is red if any of the lines below is red. The green rate therefore looks lower at the upper tiers; that is normal.
- If there is no red for a whole month, the criterion is too loose; tighten it. The board exists to show problems.
Common mistakes
- Turning into a reporting meeting: everyone reads their own numbers and nobody decides. The numbers are already on the board; only the reds are discussed.
- No escalation: a problem circles at Tier 1 for weeks because there is no written rule or time limit for moving it up.
- Actions without dates: "will check" or "to be followed up" is not an action. Without an owner and a due date, the row does not count.
- Drifting start times: if Tier 1 starts late, Tier 2 and Tier 3 meet without data.
- The manager taking over: the line leader runs Tier 1; the supervisor listens and asks questions if needed.
- Painting everything green: if red feels like a punishment, nobody writes red. Leaders who report red should be recognised.
How to start in 4 weeks
| Week | What to do |
|---|---|
| 1 | Choose a pilot line. Write the SQDCP criteria together with the line leader, put the board next to the line and fix the Tier 1 time. |
| 2 | Hold Tier 1 every day; the supervisor only listens and keeps time. Start the action list and accept no row without a date. |
| 3 | Set up Tier 2: area board, time, participants, escalation rule. The pilot line's reds start being discussed at Tier 2. |
| 4 | Review the first month's green-day rates and overdue actions; adjust the criteria and agenda. Roll out to other lines and schedule Tier 3. |
In the first two weeks the meeting may run over 20 minutes; have the timekeeper note it every day. If the 15-minute target still fails after week four, there are usually two reasons: the talk per letter is too long, or root causes are being discussed in the meeting.
Ask yourself
- Does your Tier 1 meeting start at the same time every day and finish within 15 minutes?
- Is the red criterion for each letter written down and measurable?
- Did at least one topic move from Tier 1 to Tier 2 this month, and did the answer come back to the line?
- Does every open action have a single owner and a due date?
- Can you say right now how many actions are overdue?
- Is more meeting time spent reading numbers or making decisions?
Free Excel template
The Tier Board (SQDCP) template I prepared with this guide works with two input sheets: the Daily Log (date, line, Green/Red for S, Q, D, C, P and a note) and Actions (owner, due date, status, escalation tier and date). With a line and month filter, the dashboard shows the day × letter calendar, the green-day rate, red days, open and overdue actions, this month's escalations, actions opened and closed per week and a table by line. The Lists sheet contains sample red criteria and tier rules; adapt them to your plant. Sample data is fictitious: 4 lines, 6 months.
When Excel is no longer enough
As the number of lines grows and Tier 2/Tier 3 boards need data from several lines on the same morning, a shared Excel file gets locked and actions get lost in e-mails. In the Performance and Meetings section of the TAKMOS Production Module, the SQDCP status entered by the line leader appears on the upper-tier boards at once, and actions and escalations reach their owners as notifications.