PLANNING · 02 / 05

Staffing

The manning factor per mould (0.25 = one operator tends four machines) is multiplied by machine load to give weekly man-hours and people per shift. The requirement is compared by department with actual and target headcount in HR. If there is a gap, a hiring action is opened for HR; if the target headcount is not enough, a target headcount revision request is opened.

Evidence mapping: IATF 7.1.1IATF 7.1.2VDA 6.3 P6.3
Process

From load to headcount decision

1LoadMachine × week load comes from Orders and Capacity
2FactorMan-hours from the mould's manning factor; setup hours are added
3RequirementPeople from number and length of shifts; indirect staff are added
4ComparisonRequirement, actual headcount and target headcount by department
5DecisionHiring action for a shortfall, revision request when the need exceeds the target
6ApprovalThe target headcount request is updated after approval by HR, then Top Management

The target headcount comparison covers blue-collar staff only (operators and team leaders).

Screens

Main screens of the section

Staffing requirement
02.1Staffing requirementLoad, man-hours and people per shift for each week; moulds without a manning factor are listed separately.
Target headcount comparison
02.2Target headcount comparisonPeak-week requirement, current and target headcount by department; hiring and target revision requests are opened here.
Staff management
02.3Staff managementAnalysis of current versus required staff, weekend overtime plan and monthly staff cost forecast.

Document outputs

Staffing Requirement Table

A4 landscape PDF · running machines, total load, man-hours, shifts and total staff per week

Links to other sections and modules

  • HRActual and target headcount are read from HR; hiring actions and revision approvals go to HR
  • HR (PDKS time and attendance)Approved overtime records arrive weekly in the FM Overtime Report
  • Top ManagementFinal approval of the target headcount revision request
  • 01 Orders and CapacityMachine load is the input to the requirement
Related

Guides, templates and features

FAQ

Frequently asked questions

What is the manning factor?

It is the ratio of operators working on a machine: 0.25 means one operator tends four machines, 1 means one operator per machine, 2 means two operators. Moulds without a factor are listed separately.

Who approves a target headcount request?

Planning opens a draft and sends it to HR for approval; after HR approval, Top Management approves. Once approved, the target headcount in HR is updated; the request can be rejected at any step.

Where does overtime data come from?

With a server connection, approved overtime records in HR are read weekly for production departments; operators and indirect staff are kept separate. Weekend overtime can also be entered manually.