How to prepare a PFMEA: the AIAG-VDA 7 steps and action priority (AP)
Hüseyin Şamlı · 2026-11-08 · 9 min read
A PFMEA (process failure mode and effects analysis) brings together, in one table, what can go wrong in a manufacturing process, how it would reach the customer and what you currently do to prevent it. A well-prepared PFMEA is the source of the control plan, the work instructions and your error-proofing (poka-yoke) investments; a poorly prepared one is a form filled in the week before the audit. In this guide I explain the 7 steps of the AIAG-VDA approach, what the S/O/D ratings mean, why action priority (AP) replaced the RPN and how to link the PFMEA to the control plan. A free Excel template is at the end.
What is a PFMEA and when do you do it?
A PFMEA is a preventive risk analysis carried out while the process is being designed. The DFMEA looks at the risks of the product design; the PFMEA asks: "even if the part is designed correctly, what can go wrong when we make it on this line, with these machines and these people?" The first version is prepared before the line is built and before the control plan is written; after that it stays a living document. Update it when:
- a new product or a new line is launched,
- the process, a machine, a mould, the material or the layout changes,
- a customer complaint or an internal defect reveals a cause the PFMEA did not foresee (as an output of the 8D),
- actions are completed and risks are re-assessed.
In IATF 16949, the PFMEA is listed among the outputs of manufacturing process design (clause 8.3.5.2). The clauses on special characteristics (8.3.3.3), control plan (8.5.1.1) and problem solving (10.2.3) also link back to it.
The 7 steps of the AIAG-VDA approach
The AIAG-VDA FMEA Handbook, published in 2019, merged North American and German automotive practice into one method. The method has 7 steps. The table below summarises each step in my own words:
| Step | The question | Output |
|---|---|---|
| 1. Planning and preparation | What are we analysing, with whom, by when? | Scope, boundaries, team, timing |
| 2. Structure analysis | Which steps make up the process, and which work elements make up each step? | Process flow, list of operations |
| 3. Function analysis | What must each step do, and which characteristic must it deliver? | Functions and requirements |
| 4. Failure analysis | How can the function fail, what happens then, and why? | Failure chain: effect – failure mode – cause |
| 5. Risk analysis | How big is the risk with today's prevention and detection controls? | S, O, D and action priority (AP) |
| 6. Optimisation | What will we do to reduce the risk, who, by when? | Action, owner, due date, new S/O/D |
| 7. Results documentation | To whom and how do we communicate the results? | Report, updated control plan and instructions |
Steps 1–3: describe the process properly first
The first three steps are about describing the process correctly before talking about failures. In planning, define the scope (which line, which part family, from which operation to which), the team and the timing. The team should not be the quality engineer alone; process, production, maintenance and, where relevant, the tool shop and logistics belong at the table. In the structure analysis, list every operation in the process flow (OP10, OP20…) and break each one into work elements such as man, machine, material and environment. Causes are usually found in these elements. In the function analysis, write a measurable requirement for each operation: not "weld", but "weld housing and cover to achieve the specified pull-off force".
Step 4: the failure chain
The failure chain is the heart of the PFMEA. Every row has three parts: the failure mode (how the operation fails to perform its function, e.g. "short shot"), the failure effect (how this shows up at the next station, at the customer and for the end user, e.g. "clip does not seat, panel stays loose") and the failure cause (what goes wrong in a work element, e.g. "nozzle blockage"). The most common mistake is mixing these three up. "Operator error" is a category, not a cause; a cause must be specific and must be something a control can address.
What do S, O and D tell you?
In the risk analysis, each failure chain is rated with three numbers from 1 to 10:
- S – Severity: how serious the failure effect is. The highest ratings are used when safety or a legal requirement is affected. S belongs to the effect; adding controls does not lower it, only a change to the product or process design does.
- O – Occurrence: how often the cause can occur with the current prevention control. The real question is not "how often did it happen?" but "how effective is my prevention control?"
- D – Detection: how well the current detection control catches the failure before it reaches the customer. A random visual check gets a high D; a system that detects automatically in station and stops the part gets a low D.
A prevention control stops the cause from occurring (locked recipe, poka-yoke fixture, planned maintenance); a detection control catches the failure or the cause once it has occurred (camera, leak test, measurement). If you write both in the same cell, rating O and D correctly becomes impossible.
Base your ratings on the tables in the handbook and on your customer-specific requirements; the team rating everything on the same scale matters more than the table itself. The Lists sheet of the template has our own short description for each rating; these are not the handbook tables, only a guide for the team.
Action priority (AP) instead of RPN
In the old method S × O × D was multiplied and the resulting risk priority number (RPN) was compared with a threshold ("action above RPN 100", for example). This had two weaknesses:
- It gives the three ratings equal weight. S=9, O=3, D=3 and S=3, O=9, D=3 give the same RPN (81), yet the first is a safety risk.
- Thresholds invite gaming: the team lowers D by one point to get under the line, and the real risk does not change.
Action priority (AP) therefore drops the multiplication and assigns every combination of S, O and D to High, Medium or Low priority. The logic starts with severity, then looks at occurrence and finally at detection. AP is not a risk class but a priority for action:
- High: an action to improve prevention or detection must be defined, or the reason why current controls are adequate must be justified in writing.
- Medium: an action is expected; if none is taken, the justification is recorded.
- Low: an action may be taken but is not required.
For a binding AP decision you need the AP table in the AIAG-VDA Handbook; that table is not reproduced here. The AP column in the template uses a simplified rule that follows the same order (S first, then O, then D). It is good enough for a first assessment and for prioritising; check any PFMEA you submit to a customer against the handbook table.
Optimisation: how to choose actions
When you define actions for rows with High and Medium AP, the order of preference is:
- Change the product or process design to reduce severity. It is usually the most expensive option, but the only one that lowers S.
- Reduce occurrence with a prevention control that removes the cause: locked parameters, a poka-yoke fixture, a machine with an alarm.
- Improve detection: the failure is caught automatically in station and the part cannot move on.
Actions such as "operator training" or "pay attention" do not lower O or D for good. Give every action an owner and a due date. When the action is complete, look at the evidence (trial result, photo, calibration record) and then enter the new S/O/D. A planned action does not reduce the risk; recalculate the AP only once the action is in place.
Linking the PFMEA to the control plan
The most important output of step 7 is an up-to-date control plan. The prevention and detection controls in the PFMEA should appear in the control plan as control methods, and rows marked as special characteristics (CC/SC) should carry the same symbol in the control plan. A practical rule: a control that is in the control plan but has no counterpart in the PFMEA, or one that is in the PFMEA but missing from the control plan, becomes an audit finding. Using the same operation numbers in the process flow, the PFMEA and the control plan makes this matching much easier.
What auditors ask
- Who prepared the PFMEA, and is the team cross-functional?
- Has your latest customer complaint been added to the PFMEA? Which row, which revision?
- Do rows with AP High have an action or a justification? Are any due dates overdue?
- Do the methods in the control plan match the controls in the PFMEA?
- Are special characteristics consistent across the PFMEA, the control plan and the work instructions?
The 6 most common mistakes
- A PFMEA copied from the previous project and not adapted to the new product.
- Failure mode, effect and cause written in the same cell or swapped around.
- Not separating prevention and detection controls; rating O and D against the same control.
- Rows closed with "operator error" and "training will be given".
- Entering new S/O/D before the action is complete.
- Not updating the PFMEA after complaints and internal defects, so the document stays on the same revision for years.
Free Excel template
The PFMEA Excel template comes filled with 10 operations and 25 failure chains from a fictional plastic part line (injection moulding, ultrasonic welding, assembly, test, packing). You pick the operation from a drop-down list and enter S/O/D; AP, current AP and overdue actions are calculated automatically. The dashboard shows the number of High/Medium/Low AP rows, open and overdue actions, AP distribution by operation and a before/after comparison. The Lists sheet holds short S/O/D descriptions and the rule the template uses. Simplified AP — for a binding decision use the AP table in the AIAG-VDA Handbook.
When Excel is no longer enough
A PFMEA does not live on its own; it changes together with complaints, 8D reports, the control plan and the work instructions. When these sit in separate files, a revision in one does not reach the others. In the Control Plan and FMEA section of the TAKMOS Quality Module, control plan rows are linked to PFMEA rows; the proposal from step D7 of the 8D report puts the PFMEA and the control plan into revision and flags the affected rows.